Owners of projects requiring special inspection or testing submit this agreement to Marysville with a structural tests and inspections schedule for review.

What this form is

This agreement records the owner’s, general contractor’s, and inspection or testing agency’s acknowledgments for a project requiring special inspection or testing. The document says the owner must complete, sign, and submit it before a building permit is issued, along with two copies of the structural tests and inspections schedule for review and approval. It also lists inspection and testing responsibilities during construction.

Who needs it

Owners of projects requiring special inspection or testing, along with the applicable contractor and inspection or testing agency, complete the relevant acknowledgments.

How to submit it

Return the completed form to the City of Marysville and submit two copies of the structural tests and inspections schedule to the Building Inspection Division for review and approval.

About notarization

This document is signed without a notary; the owner and applicable parties sign and date their acknowledgments, with no notarized or sworn attachment specified.

How to submit this form

  1. 1

    Download The Agreement

    Download the Special Inspection and Testing Agreement and its structural tests and inspections schedule.

  2. 2

    Complete The Form

    The owner completes and signs the form on the advice of the project engineer or architect; applicable parties complete their acknowledgments.

  3. 3

    Prepare The Schedule

    Complete the structural tests and inspections schedule and prepare two copies for review and approval.

  4. 4

    Submit To The City

    Return the agreement to the City of Marysville and submit the schedule copies to the Building Inspection Division.

Frequently asked questions

Do I need a notary for the Special Inspection and Testing Agreement?
No. The document has signature and date lines but no notary block or notarized attachment; the signer just signs and dates it.
Who completes the Special Inspection and Testing Agreement?
The owner completes and signs the form on the advice of the project engineer or architect. The form also has acknowledgments for the general contractor and inspection or testing agency, where applicable.
How do I submit the Special Inspection and Testing Agreement?
Return the completed form to the City of Marysville. Submit two copies of the structural tests and inspections schedule to the Building Inspection Division for review and approval.

Need something notarized?