Roselle, IL · DuPage County
Demolition Permit Packet
This packet explains Roselle’s demolition permit requirements and the application materials homeowners and contractors submit through the Village permitting portal.
What this form is
Use this packet when applying for a Village of Roselle demolition permit. It outlines site preparation, utility disconnections, permit fees, inspections, and construction requirements, and explains that applicants submit a completed Building Permit Application, a current plat of survey, a structure photo, and a contract if available. Contractors must have a current license before the permit is released.
Who needs it
Homeowners and contractors planning demolition in Roselle need to apply for a permit and provide the listed application materials.
How to submit it
Create an account at us.cloudpermit.com and submit through the Village permitting portal; electronic copies are preferred. Permits and contractor registration can be paid online through Cloudpermit.
About notarization
This document has no notary block; it lists no sworn or notarized attachment, and the application is submitted through Cloudpermit.
How to submit this form
- 1
Download the Packet
Download the Demolition Permit Packet to review the requirements and application materials.
- 2
Complete the Application
Create a Cloudpermit account and complete the Building Permit Application with all contractors listed.
- 3
Gather Required Materials
Prepare a current plat of survey, a picture of the structure, and a copy of the contract if available.
- 4
Submit to the Village
Submit the application and materials through the Village permitting portal at us.cloudpermit.com.
Frequently asked questions
- What materials are needed for a Roselle demolition permit?
- The packet lists a completed Building Permit Application with contractors listed, a current plat of survey, a picture of the structure, and a copy of the contract if available.
- How do I submit the demolition permit application?
- Create an account at us.cloudpermit.com and submit through the Village permitting portal. The packet says electronic copies are preferred.
- Do I need a notary for the Demolition Permit Packet?
- No. The packet has no notary block and lists no sworn or notarized attachment; the application is submitted through Cloudpermit.
- When can demolition work begin?
- Work cannot begin until the permit has been issued and paid. The packet also says the Village electrical inspector must approve electrical disconnection before demolition starts.