Rock Falls, IL · Whiteside County
Customer-Owned Generating Facilities Interconnection Agreement
This agreement sets terms for connecting a customer-owned generating facility to the City of Rock Falls electric distribution system and is signed by the customer and City.
What this form is
The agreement governs how a customer-owned generating facility connects to and operates in parallel with the City of Rock Falls electric distribution system. Customers seeking interconnection must complete and return an Interconnection Request Application Form with the applicable processing fee; the agreement records the parties’ responsibilities, technical requirements, insurance obligations, and signatures. It also identifies related documents, including a one-line drawing and Certificate of Completion.
Who needs it
A City of Rock Falls electric customer proposing to install or own a generating facility, or add generating capacity to an existing facility, needs this agreement.
How to submit it
Submit it to the city department named on the form; check the city website for current contact details.
About notarization
This agreement is signed without a notary; it lists attachments, including an application and completion certificate, but does not say they must be notarized.
How to submit this form
- 1
Download the Agreement
Download the Customer-Owned Generating Facilities Interconnection Agreement PDF.
- 2
Complete the Agreement
Fill in the customer information and other applicable fields, then review the terms and responsibilities.
- 3
Gather Related Documents
Gather the one-line drawing, Interconnection Request Application Form, System Upgrade Estimated Costs, and Certificate of Completion identified in the agreement.
- 4
Submit to the City
Submit it to the city department named on the form; check the city website for current contact details.
Frequently asked questions
- Do I need a notary for the generating facility interconnection agreement?
- No. This agreement is signed without a notary. It lists related documents, including an application and completion certificate, but does not say they must be notarized.
- Who signs the interconnection agreement?
- The agreement is between the City of Rock Falls Electric Department and the customer who owns the generating facility. It includes signature fields for both parties.
- How do I submit the interconnection agreement?
- Submit it to the city department named on the form; check the city website for current contact details.
- What other documents does the agreement identify?
- The agreement identifies a one-line drawing, Interconnection Request Application Form, System Upgrade Estimated Costs, and Certificate of Completion as attached and incorporated documents.