Hudson, MI · Lenawee County
Electrical Permit Application
Contractors and homeowners use this application to request a City of Hudson permit before starting electrical installation work.
What this form is
The application requests a permit for new, remodeled, service-only, special-inspection, and other electrical work in Hudson. It asks for the job location, owner or contractor details, type of work, plan-review information, and itemized fee calculations. Plans are required for work not covered by the form’s stated exceptions, and the form says they must be submitted before a permit can be issued.
Who needs it
A contractor or homeowner must file this application with the City of Hudson before starting electrical work.
How to submit it
File the application with the City of Hudson at 121 N. Church St., Hudson, MI 49247; make checks payable to City of Hudson. The form lists (517) 448-8983.
About notarization
This application is signed without a notary; a homeowner applying as the installer must also sign the homeowner affidavit, and the form does not require notarization.
How to submit this form
- 1
Download The Application
Download the Electrical Permit Application PDF.
- 2
Complete The Application
Enter the job location, owner or contractor details, work type, plan-review information, and applicable fee items; sign the application.
- 3
Gather Required Plans
If plans are required, submit plans prepared by or under the direct supervision of a licensed architect or engineer, bearing their signature and seal.
- 4
Submit To The City
File the application with the City of Hudson at 121 N. Church St., Hudson, MI 49247, and make checks payable to City of Hudson.
Frequently asked questions
- Do I need a notary for the Electrical Permit Application?
- No. The application does not require notarization. A homeowner applying as the installer must also sign the homeowner affidavit.
- How do I submit the Electrical Permit Application?
- File it with the City of Hudson at 121 N. Church St., Hudson, MI 49247. Make checks payable to City of Hudson.
- What information does the application ask for?
- It requests the job location, owner or contractor information, type of electrical work, plan-review details, and an itemized fee calculation.
- When are plans required?
- The form says plans are required for work outside its listed exceptions and must be submitted before a permit can be issued.