Carrollton property owners or their agents use this application to request building or zoning approval for construction, alterations, and other listed projects.
What this form is
The application requests building permit and zoning information, including the property tax ID, owner and project details, structural specifications, and proposed use. Carrollton requires a completed application and supporting plans or sketches, plus a plot plan for zoning review; the document says to submit at least 15 days before the anticipated project start. The attached fee schedule lists fees for different project types.
Who needs it
Property owners or their agents planning construction, alterations, or another project covered by the building or zoning application should complete the relevant sections.
How to submit it
Return the completed application with two sets of plans or sketches and required supporting documents to the Town of Carrollton, 640 Main Street, Suite 1, Limestone, NY 14753. The document lists permit fees by project type.
About notarization
This application is signed without a notary; the document says a homeowner may need a notarized BP-1 form for certain workers’ compensation insurance exemptions.
How to submit this form
- 1
Download The Application
Download the building and zoning permit application and fee schedule.
- 2
Complete The Relevant Sections
Fill in the project and property information, including the property description number found on the property tax bill.
- 3
Gather Plans And Attachments
Include two sets of plans or sketches, a plot plan for zoning review, and required insurance certificates or other documents.
- 4
Submit To The Town
Return the completed application and required materials to the Town of Carrollton at 640 Main Street, Suite 1, Limestone, NY 14753.
Frequently asked questions
- Do I need a notary for the Building and Zoning Permit Application?
- No. This application is signed without a notary. The document says a homeowner may need a notarized BP-1 form for certain workers’ compensation insurance exemptions.
- How do I submit the Building and Zoning Permit Application?
- Return the completed application with two sets of plans or sketches and required documents to the Town of Carrollton, 640 Main Street, Suite 1, Limestone, NY 14753.
- What should I include with the application?
- Include two sets of plans or sketches and a plot plan showing buildings, dimensions, setbacks, and other details listed in the application. Include insurance certificates or other required documents.
- When should I submit the application?
- The document says a completed application must be submitted at least 15 days before the anticipated project start. Incomplete applications and plans will be returned and may delay approval.