Schoharie, NY · Schoharie County
Floodplain Development Permit Application
Applicants use this application to request review of proposed development and construction activities in Schoharie’s floodplain areas.
What this form is
The application records the proposed project, its location, the applicant and project team, and the type and estimated cost of the work. Applicants complete Sections 1 and 2 and submit the form for review; the Local Administrator determines whether the project is in a Special Flood Hazard Area and whether additional documents are needed. The form also describes permit conditions and later as-built elevation information required before a Certificate of Compliance.
Who needs it
Applicants proposing structural or other development activities in Schoharie should complete this form for Local Administrator review.
How to submit it
Complete the form in duplicate and submit it to the Local Administrator for review. If approved, the Local Administrator may issue the permit upon payment of the designated fee.
About notarization
This application is signed and dated without a notary; the applicant just signs and dates it, while specified engineer certifications are submitted as attachments.
How to submit this form
- 1
Download The Application
Download the Floodplain Development Permit Application.
- 2
Complete The Applicant Sections
Complete Sections 1 and 2 with applicant and project details, then sign and date the application.
- 3
Gather Required Documents
Include the documents requested by the Local Administrator, such as plans or applicable engineer or architect certifications.
- 4
Submit For Review
Submit the completed form in duplicate to the Local Administrator for review.
Frequently asked questions
- What is the Floodplain Development Permit Application for?
- It gives the Local Administrator information to review proposed development, determine floodplain status, and identify any additional documents needed.
- Who completes this application?
- The applicant completes Sections 1 and 2 with contact, project location, proposed work, and estimated cost information. The form says to submit it in duplicate.
- Do I need a notary for the Floodplain Development Permit Application?
- No. The applicant signs and dates this application without a notary. Specified certifications from a registered engineer or architect may be required as attachments.
- How do I submit the Floodplain Development Permit Application?
- Complete the form in duplicate and submit it to the Local Administrator for review. If approved, the permit may be issued upon payment of the designated fee.