This application supports a Fallsburg Planning Board review of a proposed site plan or special permit project and is completed by the applicant or project sponsor.

What this form is

The document combines a site plan approval application, a site plan review checklist, a Short Environmental Assessment Form, and a legal notice template for Planning Board review. Applicants provide project, site, ownership, and development details and prepare supporting maps, environmental information, and other required materials. The document states that a special permit requires a public hearing and lists application materials and fees.

Who needs it

Applicants seeking Planning Board review for a proposed site plan or special permit in Fallsburg should complete this application and prepare the listed supporting materials.

How to submit it

File the application and required materials with the Code Enforcement Office at 5250 Main Street, South Fallsburg, NY 12779. The document lists fees and says materials must be on file at least 15 days before a scheduled meeting.

About notarization

This document is signed and dated without a notary; it does not identify any attachment or related step that must be notarized or sworn.

How to submit this form

  1. 1

    Download The Application

    Download the Fallsburg Special Permit Application PDF.

  2. 2

    Complete The Application

    Enter the applicant, project, site, ownership, and development information requested in the application and environmental form.

  3. 3

    Gather Supporting Materials

    Prepare the listed maps, environmental form, tracking document, adjoining-owner information, and required application packets.

  4. 4

    Submit To The Code Enforcement Office

    File the application and required materials at 5250 Main Street, South Fallsburg, NY 12779, at least 15 days before the scheduled meeting.

Frequently asked questions

Do I need a notary for the Special Permit Application?
No. This document is signed and dated without a notary, and it does not identify an attachment or related step that must be notarized or sworn.
How do I submit the Special Permit Application?
File it with the Code Enforcement Office at 5250 Main Street, South Fallsburg, NY 12779, along with the required materials. The document says materials must be on file at least 15 days before the meeting.
What supporting materials does the application list?
The document lists project maps, an Environmental Assessment Form, a tracking document, adjoining-owner information, and packets of application materials. Its site plan checklist also identifies plans and project details for review.
Does a special permit require a public hearing?
Yes. The application instructions state that a public hearing is mandatory for special permits and describe legal notice requirements for adjoining property owners.