Brisbane, CA · San Mateo County

No notary required

Construction and Demolition Debris Recycling and Waste Reduction Plan

Applicants use this plan to estimate project debris, choose a waste-management method, and document recycling for covered construction and demolition projects in Brisbane.

What this form is

This plan is required with a building permit application for covered demolition, renovation, remodel, addition, and re-roofing projects. It asks for project, owner, and contractor information; estimated debris quantities; a deposit calculation; and the selected waste-management method. The form also describes diversion requirements and documentation to provide when the project is complete.

Who needs it

Applicants for covered demolition, renovation, remodel, addition, and re-roofing projects complete this plan with their building permit application.

How to submit it

Complete this plan with the Building Permit application. At project completion, provide original recycling-company or approved-facility receipts to the City of Brisbane Community Development Department to request a refund.

About notarization

This document is signed without a notary; the applicant signs the completed plan to certify its accuracy, then dates the staff-use section when payment is recorded.

How to submit this form

  1. 1

    Download The Plan

    Download the Construction and Demolition Debris Recycling and Waste Reduction Plan.

  2. 2

    Complete Project Information

    Enter project, owner, and contractor details, estimate debris quantities, calculate the deposit, and select a waste-management method.

  3. 3

    Gather Receipts

    Keep original receipts from recycling companies or approved facilities for submission at project completion.

  4. 4

    Submit With Your Permit Application

    Submit the completed plan with the Building Permit application; provide the original receipts to Community Development at project completion.

Frequently asked questions

Who must complete the Construction and Demolition Debris Recycling and Waste Reduction Plan?
Applicants for covered demolition, renovation, remodel, addition, and re-roofing projects complete the plan with the Building Permit application.
What information does the plan request?
It requests project, owner, and contractor details, estimated debris quantities, a deposit calculation, and the selected waste-management method.
Do I need a notary for the Construction and Demolition Debris Recycling and Waste Reduction Plan?
No. The document has no notary block. The applicant signs the completed plan to certify its accuracy; the form does not call for a notarized attachment.
How do I submit the Construction and Demolition Debris Recycling and Waste Reduction Plan?
Complete it with the Building Permit application. At project completion, provide original recycling-company or approved-facility receipts to the City of Brisbane Community Development Department to request a refund.

Need something notarized?