Commercial Net Metering and Interconnection Application

Commercial electric customers use this application to request approval to interconnect an eligible customer-owned generating facility and receive net metering service from Waterloo.

What this form is

This application is part of Waterloo’s commercial net metering policy and interconnection agreement. Customers must complete the application and receive approval from the Director of Public Works before construction starts; the contractor must deliver a Certification of Completion before the facility’s in-service date. The application supports review of the generating facility and its effect on the distribution system.

Who needs it

A commercial electric customer planning to install or add a qualifying customer-owned generating facility at a Waterloo service location needs to submit this application.

How to submit it

Return the Interconnection Request Application Form to the Utility with the applicable processing fee: $200 for systems sized 25 kW AC and under, or $350 for systems greater than 25 kW AC.

About notarization

This document is signed without a notary; it identifies no notarized attachment or sworn step, so the signer just signs and dates it.

How to submit this form

  1. 1

    Download The Application

    Download the commercial net metering and interconnection PDF.

  2. 2

    Complete The Application

    Fill in the Interconnection Request Application Form with the information requested for the customer and generating facility.

  3. 3

    Gather Required Materials

    Include the applicable processing fee: $200 for systems 25 kW AC and under, or $350 for systems greater than 25 kW AC.

  4. 4

    Submit To The Utility

    Return the completed application and applicable processing fee to the Utility for review.

Frequently asked questions

Do I need a notary for the Commercial Net Metering Application?
No. This document is signed without a notary, and it identifies no notarized attachment or sworn step; the signer just signs and dates it.
How do I submit the Commercial Net Metering Application?
Return the Interconnection Request Application Form to the Utility with the applicable processing fee. The document lists $200 for systems 25 kW AC and under and $350 for systems greater than 25 kW AC.
When must I apply for interconnection?
The customer must complete the application and receive approval from the Director of Public Works before the project starts construction.
What must the contractor provide before the facility goes into service?
Before the project’s in-service date, the contractor must complete and deliver the Certification of Completion to the Director of Public Works.