This application helps Hollister project applicants determine and document which post-construction stormwater requirements apply to their development project.
What this form is
Project applicants use this document to assess whether their project is subject to post-construction requirements and identify which stormwater control forms and supporting materials are needed. It asks for project and site details, impervious surface areas, runoff strategies, treatment and retention information, and supporting calculations or documentation when applicable. Requirements depend on project type and area thresholds described in the document.
Who needs it
Applicants for development projects in Hollister use this document to identify applicable stormwater requirements and prepare the required forms and attachments.
How to submit it
The document identifies the City of Hollister Development Services Engineering Department at 339 Fifth Street, Hollister, CA 95023. It does not specify a submission method.
About notarization
This document is completed without a notary; the required Engineer of Record certification is signed and sealed, and no notarized attachment is identified.
How to submit this form
- 1
Download The Document
Download the Stormwater Management Post-Construction Requirements PDF.
- 2
Complete Project Information
Enter the requested applicant, project, location, project type, and site-area information.
- 3
Identify Applicable Requirements
Follow the project-type and area thresholds to determine which of Forms 1 through 4 apply.
- 4
Gather Required Attachments
Prepare the applicable plans, calculations, supporting documents, and Engineer of Record certification described in the forms.
- 5
Submit To The City
The document lists the Development Services Engineering Department at 339 Fifth Street, Hollister, CA 95023; it does not state how to submit.
Frequently asked questions
- Do I need a notary for the Stormwater Management Post-Construction Requirements?
- No. The document has no notary block; it requires an Engineer of Record to sign and seal the certification. No notarized attachment is identified.
- How do I submit the stormwater requirements application?
- The document lists the Hollister Development Services Engineering Department at 339 Fifth Street, Hollister, CA 95023, but does not specify a submission method.
- Which stormwater forms may be required?
- Depending on project type and area thresholds, the document directs applicants to complete Forms 1 through 4 for site design and runoff reduction, water quality treatment, runoff retention, and peak management.
- What information does the document ask for?
- It asks for project and site information, impervious surface areas, runoff strategies, and, when applicable, supporting calculations, plans, and other documentation.
Need something notarized?