Millbrae’s Building Division application lets owners, architects, engineers, or contractors request approval to use alternate materials, designs, or construction methods on a project.
What this form is
Use this application to request approval for an alternate material, design, or construction method for a project in Millbrae. It asks for project and building details, the subject of the alternative, the applicable code requirement, the proposed alternative, and justification; applicants must submit two copies of supporting documents, including plans.
Who needs it
Owners, architects, engineers, or contractors seeking approval for an alternate material, design, or construction method can submit this application.
How to submit it
Submit two copies of all documents, including plans, to the Community Development Department’s Building Division at 621 Magnolia Avenue, Millbrae, CA 94030. The form states a $534 fee is due upon submittal.
About notarization
This document is signed without a notary; it calls for owner, architect or engineer, and contractor signatures, and the signer just signs and dates it.
How to submit this form
- 1
Download The Application
Download the alternate materials, design, or construction methods application.
- 2
Complete The Application
Enter project details and describe the alternative, applicable code requirement, proposal, and justification.
- 3
Gather Supporting Documents
Include two copies of all documents, including plans showing the proposed alternate; attachments must be 8½×11 or 11×17 inches.
- 4
Submit To The Building Division
Submit the application and two copies to the Community Development Department’s Building Division at 621 Magnolia Avenue, Millbrae, CA 94030.
Frequently asked questions
- What does the alternate materials application request?
- It requests approval to use an alternate material, design, or construction method and asks for project information, code requirements, the proposed alternative, and justification.
- Who can submit this application?
- The form provides signature fields for an owner, architect or engineer, and contractor. It requests approval for an alternative used on a project.
- Do I need a notary for the alternate materials application?
- No. This application is signed without a notary; it calls for owner, architect or engineer, and contractor signatures, and the signer just signs and dates it.
- How do I submit the alternate materials application?
- Submit two copies of all documents, including plans, to the Community Development Department’s Building Division at 621 Magnolia Avenue, Millbrae, CA 94030. The form states a $534 fee is due upon submittal.