Lumpkin County, GA · Lumpkin County
Water System Flow Test Request
Owners, design professionals, technicians, or their agents use this request to seek water system flow tests from the Lumpkin County Water & Sewerage Authority.
At a glance
- Issued by
- City of Lumpkin County · Lumpkin County, Lumpkin County, Georgia
- Notarization
- Not required: file this form without a notary.
- Official source
- lumpkincounty.gov
- Blank form
- Download the PDF
- Catalogued
- Machine-readable
- JSON record · about the forms index
What this form is
This request lets an owner, design professional, technician, or agent seek tests such as fire flow, residual pressure measurements, pressure recording, or water quality sampling. The Authority requires at least one week’s notice to prepare and schedule tests, and the applicant must pay a $250 inspection fee. The form asks for contact details, project location, requested dates and tests, and information about test personnel.
Who needs it
An owner, design professional, technician, or agent seeking water system flow data or a scheduled test should submit this request.
How to submit it
Submit the request to the Engineering Department of the Lumpkin County Water & Sewerage Authority. The document requires at least one week’s notice and a $250 inspection fee.
About notarization
This request has no notary block; it lists no sworn or notarized attachment, and the form provides no signature or date field.
How to submit this form
- 1
Download the Request
Download the Water System Flow Test Request.
- 2
Complete the Request
Provide the owner or agent name and contact information, project location, requested dates and tests, and test personnel details.
- 3
Prepare Test Information
List participants, qualifications, and tools. The policy says the agent should furnish measurement equipment if accuracy is desired.
- 4
Submit to the Authority
Submit the request to the Engineering Department with at least one week’s notice and pay the $250 inspection fee.
Frequently asked questions
- What tests can I request?
- The policy lists fire flow, residual pressure measurements, 24-hour pressure recording, water quality sampling, and other flow estimates as available test types.
- How much notice and what fee are required?
- The Authority requires at least one week’s notice to prepare and schedule a test. The applicant must pay a $250 inspection fee.
- Do I need a notary for the Water System Flow Test Request?
- No. The request has no notary block and lists no sworn or notarized attachment; it also provides no signature or date field.
- How do I submit the Water System Flow Test Request?
- Submit it to the Engineering Department of the Lumpkin County Water & Sewerage Authority, with at least one week’s notice and the $250 inspection fee.