Chagrin Falls, OH · Cuyahoga County
Right-of-Way Permit Application for Sewer, Water, Driveway, and Sidewalk Work
Property owners, contractors, or applicants use this application to request a right-of-way permit for sewer, water, driveway, sidewalk, and related work.
What this form is
This application requests a permit for proposed right-of-way work, including sewer, water, driveway, sidewalk, gas service, and related connections. It asks for property owner and contractor details, work scope and location, materials, dates, estimated construction cost, and restoration plans. The form states that fees are due when the application is submitted, incomplete applications will not be processed, and other departments may need to approve the permit.
Who needs it
A property owner, contractor, or other applicant planning the right-of-way work listed on the form should complete the application.
How to submit it
The form lists the Building Department email as [email protected] and the address as 21 W. Washington Street, Chagrin Falls, OH 44022. It says all fees are due at submission and approved permits will be emailed.
About notarization
This document is signed without a notary; the applicant signs and dates the form, and no notarized or sworn attachment is mentioned.
How to submit this form
- 1
Download The Application
Download the right-of-way permit application PDF.
- 2
Complete The Form
Enter the owner, contractor, and applicant information and describe the proposed work, materials, dates, and work limits.
- 3
Gather Supporting Details
Provide a site or location plan detailing where the proposed work will take place; the form also notes that a cash performance bond may be required.
- 4
Submit To The City
Submit the application with all fees due at submission. The form lists the Building Department email and street address, and says approved permits will be emailed.
Frequently asked questions
- Who should complete the right-of-way permit application?
- The form collects information from the property owner, general contractor, subcontractor, and applicant about the proposed work and its location.
- What information does the application request?
- It asks for owner and contractor contact details, work scope and limits, materials, utility coordination, start and restoration dates, and estimated construction cost.
- Do I need a notary for the right-of-way permit application?
- No. The applicant signs and dates this form; it does not mention a notarized or sworn attachment.
- How do I submit the right-of-way permit application?
- The form lists [email protected] and 21 W. Washington Street, Chagrin Falls, OH 44022. It says fees are due at submission and approved permits will be emailed.
Need something notarized?
This Right-of-Way Permit Application for Sewer, Water, Driveway, and Sidewalk Work doesn’t need a notary — but if you have another Chagrin Falls form that does, a commissioned online notary can help.