Utility companies and contractors use this permit application to request permission to occupy a Canal Winchester street, sidewalk, alley, right of way, or easement.

What this form is

This application requests permission to perform utility work in a public street, alley, sidewalk, right of way, or easement in Canal Winchester. Applicants provide company and contact details, the work location, and the purpose of the work, and must submit scaled plans, including a maintenance of traffic plan. Permit conditions cover restoration, work hours, fees, notices, and required as-built drawings.

Who needs it

A utility company or contractor planning work that occupies a Canal Winchester public street, alley, sidewalk, right of way, or easement needs this permit.

How to submit it

Submit the application to the Department of Construction Services, 45 East Waterloo St., Canal Winchester, Ohio 43110. The form lists work permit fees and requires scaled plans, including a maintenance of traffic plan.

About notarization

This document is signed and dated without a notary; it does not identify any attachment or related step that must be notarized or sworn.

How to submit this form

  1. 1

    Download The Permit

    Download the Right of Way Utility Permit PDF.

  2. 2

    Complete The Application

    Provide company and contact details, the work location, and the purpose of the proposed work.

  3. 3

    Gather Required Plans

    Attach scaled plans of the proposed work, including a maintenance of traffic plan.

  4. 4

    Submit To The City

    Submit the application to the Department of Construction Services at 45 East Waterloo St., Canal Winchester, Ohio 43110.

Frequently asked questions

Who uses the Right of Way Utility Permit?
Utility companies and contractors use the application to request permission to occupy a public street, alley, sidewalk, right of way, or easement in Canal Winchester.
What must I include with the application?
The form requires scaled plans of the proposed work, including a maintenance of traffic plan. It also asks for company and contact information, the work location, and the purpose.
How do I submit the Right of Way Utility Permit?
Submit it to the Department of Construction Services at 45 East Waterloo St., Canal Winchester, Ohio 43110. The form lists fees and required plan attachments.
Do I need a notary for the Right of Way Utility Permit?
No. The application has a signature and date line but no notary block; the form does not identify any attachment or related step that must be notarized or sworn.

Need something notarized?

This Right of Way Utility Permit doesn’t need a notary — but if you have another Canal Winchester form that does, a commissioned online notary can help.