This application requests permission to perform construction in Reynoldsburg’s right of way and is completed by the applicant responsible for the work.
What this form is
Use this application to request a permit for construction in a Reynoldsburg right of way; the form states that work cannot proceed until the permit is approved. It asks for applicant, project, contractor, and construction-date information, and requires two sets of plans and other project details. Applicants requesting a road closure must also provide a traffic control plan.
Who needs it
Applicants planning construction in a Reynoldsburg right of way must complete this application and provide the listed project information and attachments.
How to submit it
Submit the application to the Department of Public Service at 7232 East Main Street, Reynoldsburg, Ohio 43068. The form lists 614-322-6810 as the department phone number.
About notarization
This document is signed without a notary; it does not identify any notarized or sworn attachment, so the applicant just signs and dates it.
How to submit this form
- 1
Download The Application
Download the Right of Way Work Permit from the Reynoldsburg city forms directory.
- 2
Complete The Application
Enter applicant, project, contractor, and construction-date details, then sign and date the application.
- 3
Gather Required Attachments
Include two sets of plans and the project details and notification statements listed on the form. Road-closure applicants must include a traffic control plan.
- 4
Submit To The Department
Submit the application to the Department of Public Service at 7232 East Main Street, Reynoldsburg, Ohio 43068.
Frequently asked questions
- What is the Right of Way Work Permit for?
- It is an application to request permission for construction in a Reynoldsburg right of way. The form says work cannot proceed until the permit is approved.
- What must I include with the application?
- The form lists a description of the affected right of way and facility, two sets of plans, work timing details, and statements about required notifications. Road-closure applicants must provide a traffic control plan.
- Do I need a notary for the Right of Way Work Permit?
- No. This document is signed without a notary; it does not identify any notarized or sworn attachment, so the applicant just signs and dates it.
- How do I submit the Right of Way Work Permit?
- Submit it to the Department of Public Service at 7232 East Main Street, Reynoldsburg, Ohio 43068. The form lists 614-322-6810 as the department phone number.