Utility companies and contractors use this application to request permission for work in a Village of Bowerston roadway or right-of-way.

What this form is

The application requests a permit for work such as digging, boring, trenching, or installing utilities in a Village roadway or right-of-way. A separate application and set of plans are required for each road, and the document says to apply at least five working days before the proposed work. Applicants provide contact, project, installation, and construction details and agree to the permit conditions.

Who needs it

Utility companies, contractors, or other applicants planning work in a Village of Bowerston roadway or right-of-way need to complete the application.

How to submit it

The application says to notify the Village Administrator by email at least 48 hours before work begins; the document also lists [email protected]. Include plans with the application.

About notarization

This document is signed and dated without a notary; the signer certifies the application and attachments but no sworn or notarized attachment is specified.

How to submit this form

  1. 1

    Download the Application

    Download the Right-of-Way Permit Application and review its conditions, requirements, and plan requirements.

  2. 2

    Complete the Application

    Fill in applicant and contractor details, project location, installation information, and anticipated construction dates.

  3. 3

    Gather the Plans

    Include a set of plans showing the proposed work. Submit a separate application and plans for each road.

  4. 4

    Notify the Village

    Notify the Village Administrator by email at least 48 hours before work begins, using the contact information in the document.

Frequently asked questions

Do I need a notary for the Right-of-Way Permit Application?
No. The application includes a signature and date line, but no notary block or notarized attachment is specified.
How do I submit the Right-of-Way Permit Application?
Include plans with the application and notify the Village Administrator by email at least 48 hours before work begins. The document lists [email protected].
What information does the application ask for?
It asks for applicant and contractor contact details, project location, utility and installation information, proposed construction dates, and project length.
Do I need a separate application for each road?
Yes. The document requires a separate right-of-way permit application with a set of plans for each road.

Need something notarized?

This Right-of-Way Permit Application doesn’t need a notary — but if you have another Bowerston form that does, a commissioned online notary can help.