Atascosa County, TX · Atascosa County
Temporary Water Line Right of Way Request and Permit
Companies use this request to seek Atascosa County approval to install a temporary water line along county roads or rights of way.
At a glance
- Issued by
- City of Atascosa County · Atascosa County, Atascosa County, Texas
- Notarization
- Not required: file this form without a notary.
- Official source
- co.atascosa.tx.us
- Blank form
- Download the PDF
- Catalogued
- Machine-readable
- JSON record · about the forms index
What this form is
This application asks Atascosa County to approve a company’s temporary water line installation along specified county roads or rights of way. It requests company and representative details, the proposed location, plans and drawings, contact information, and proposed work dates; a surveyed plat is also required. The application describes permit conditions, fees, insurance or self-insurance requirements, and the County Commissioners Court approval process.
Who needs it
A company proposing to install a temporary water line along an Atascosa County road or right of way must submit this request for Commissioners Court approval.
How to submit it
Contact the County Judge’s Office and the appropriate County Commissioner, then submit the signed request, surveyed plat, and fee check to the County Judge’s Office for Commissioners Court approval.
About notarization
This request is signed and dated without a notary; it calls for plans and a surveyed plat, but does not require those attachments to be notarized.
How to submit this form
- 1
Download the Request
Download the Temporary Water Line Right of Way Request and Permit.
- 2
Complete and Sign
Fill in the company, representative, location, contact, and proposed work details, then sign and date the request.
- 3
Gather Plans and Plat
Attach plans and drawings and provide a surveyed plat for each crossing.
- 4
Submit to the County
Contact the County Judge’s Office and appropriate County Commissioner, then submit the signed request, plat, and fee check to the County Judge’s Office.
Frequently asked questions
- Do I need a notary for the Temporary Water Line Right of Way Request and Permit?
- No. The request has a signature and date field but no notary block. It calls for plans and a surveyed plat, but does not require those attachments to be notarized.
- How do I submit the Temporary Water Line Right of Way Request and Permit?
- Contact the County Judge’s Office and the appropriate County Commissioner. Submit the signed request, surveyed plat, and fee check to the County Judge’s Office before it is placed on the Commissioners Court agenda.
- What must accompany the request?
- The document says to provide a surveyed plat for each crossing and attached plans and drawings. A fee check must accompany the request; the amount depends on the permit and any applicable fees.
- How long does the permit last?
- The document says the permit is for 90 days. It describes submitting a renewal request at least 10 days before expiration if the temporary line is expected to remain in use.