What this form is
This application gives the city notice of a proposed utility installation in a road or parcel right-of-way and requests a permit. Applicants provide owner and contractor contact details, utility and work information, and attach drawings; proof of insurance and bonding must be on file before approval. A traffic control plan is required one week in advance if the work involves a temporary road closure.
Who needs it
A contractor proposing to install a utility line within a Celina right-of-way uses this application to notify the city and request a permit.
How to submit it
Submit it to the city department named on the form; check the city website for current contact details.
About notarization
This application is signed without a notary; it identifies no sworn or notarized attachment, and the authorized contractor representative signs the form.
How to submit this form
- 1
Download The Application
Download the Right-Of-Way Utility Installation Permit Application.
- 2
Complete The Application
Enter the owner and contractor contact details, utility type, proposed location, and installation information.
- 3
Gather Required Attachments
Attach complete drawings. Ensure proof of insurance and bonding is on file; submit a traffic control plan one week in advance if a temporary road closure is planned.
- 4
Submit To The City
Return the application to the city department named on the form; check the city website for current contact details.
Frequently asked questions
- What is the Right-Of-Way Utility Installation Permit Application?
- It notifies Celina of proposed utility work in a road or parcel right-of-way and requests a permit. The form asks for owner, contractor, utility, and work details.
- Do I need a notary for the Right-Of-Way Utility Installation Permit Application?
- No. This application is signed without a notary; it identifies no sworn or notarized attachment, and the authorized contractor representative signs the form.
- How do I submit the Right-Of-Way Utility Installation Permit Application?
- The form says the application must be returned before work proceeds but does not give a submission address or department. Submit it to the city department named on the form; check the city website for current contact details.
- What attachments may be required?
- Attach a complete set of drawings. Proof of insurance and bonding must be on file before approval; if a temporary road closure is planned, submit a traffic control plan one week in advance for approval.
Need something notarized?
This Right-Of-Way Utility Installation Permit Application doesn’t need a notary — but Texas residents can notarize other documents online with a commissioned online notary.