Board of Adjustment Variance Application

Property owners or authorized applicants use this application to ask South Tucson’s Board of Adjustment for a variance or appeal.

What this form is

This application asks the South Tucson Board of Adjustment to consider a variance or appeal related to a property. It requests property ownership, address, zoning, lot size, legal description, existing and proposed uses, and the requested change and its reasons. Applicants must attach two copies of a plot plan; applications for variances for new construction must also include a building permit application.

Who needs it

Property owners or people authorized by an owner should file this application to request a Board of Adjustment variance or appeal.

How to submit it

Applications are accepted any business day during normal working hours. Make checks payable to the City of South Tucson; the form says fees are non-refundable.

About notarization

This document is signed without a notary; it requires two plot plan copies and, for new-construction variance applications, a building permit application, and the signer signs and dates it.

How to submit this form

  1. 1

    Download The Application

    Download the Board of Adjustment Variance Application PDF.

  2. 2

    Complete The Application

    Provide the property information, requested change, reasons, and applicant signature.

  3. 3

    Gather Required Attachments

    Attach two plot plan copies; include a building permit application for a variance for new construction.

  4. 4

    Submit To The City

    Submit the application during normal working hours on a business day. Make any check payable to the City of South Tucson.

Frequently asked questions

What does the Board of Adjustment Variance Application request?
It asks the Board to consider a variance or appeal and collects property details, the requested change, and the reasons for the request.
What attachments are required for this application?
Attach two copies of a plot plan showing structures on the property and nearby properties. A variance request for new construction must also include a building permit application.
Do I need a notary for the Board of Adjustment Variance Application?
No. The application is signed without a notary. It requires plot plan copies and, for new-construction variance applications, a building permit application.
How do I submit the Board of Adjustment Variance Application?
The document says applications are accepted any business day during normal working hours. Make checks payable to the City of South Tucson; fees are non-refundable.

Need something notarized?

This Board of Adjustment Variance Application doesn’t need a notary — but if you have another South Tucson form that does, a commissioned online notary can help.