Developers use this application to request Technical Review Committee input on a proposed project in the Borough of Keyport.

What this form is

Keyport’s Technical Review Committee process gives developers an opportunity to discuss project plans and receive guidance on proceeding to a Unified Planning Board hearing. The application asks for applicant, owner, engineer, attorney, property, and project details, and includes a review-fee selection and escrow form. The submission also calls for eight copies of project materials and a completed W-9.

Who needs it

Developers interested in pursuing a project in Keyport can submit this application to discuss plans and receive committee guidance.

How to submit it

Submit the application to Laurie Graham and schedule a meeting with Denise Nellis. Include eight copies of the requested project materials, a disk or thumb drive containing all submitted information, and the application and fee.

About notarization

This document is signed without a notary; the applicant signs and dates the application, and the W-9 includes its own taxpayer certification signature.

How to submit this form

  1. 1

    Download The Application

    Download the Technical Review Committee application and its included escrow form and W-9.

  2. 2

    Complete The Application

    Provide applicant, owner, engineer, attorney, property, and proposed project information, then sign and date the application.

  3. 3

    Gather Project Materials

    Prepare eight copies of the project narrative, site plan, plat, or sketch, and proposed building elevations or renderings; put all submitted information on a disk or thumb drive.

  4. 4

    Submit And Schedule

    Submit the application, materials, and fee to Laurie Graham, then schedule a meeting with Denise Nellis.

Frequently asked questions

What is the Keyport Technical Review Committee application for?
It lets developers submit project information for committee discussion and guidance on how to proceed to a Keyport Unified Planning Board hearing.
What materials should accompany the application?
The form requests eight copies of a project narrative, a site plan, plat, or sketch, and proposed building elevations or renderings. Include a disk or thumb drive with all submitted information and the attached W-9.
Do I need a notary for the Technical Review Committee application?
No. The application is signed without a notary; the applicant signs and dates it, and the W-9 has its own taxpayer certification signature.
How do I submit the Technical Review Committee application?
Submit it to Laurie Graham with the required copies, digital materials, and fee, then schedule a meeting with Denise Nellis as directed on the form.

Need something notarized?

This Technical Review Committee Application doesn’t need a notary — but if you have another Keyport form that does, a commissioned online notary can help.