Bellingham, WA · Whatcom County

No notary required

Deconstruction/Demolition Permit Application

Property owners or authorized applicants use this application to request a Bellingham permit for qualifying total or partial deconstruction or demolition projects.

What this form is

Bellingham requires a demolition permit for total demolitions of structures larger than 120 square feet and for partial demolitions not covered by a building permit. The application asks for property and project details, utility removal plans, debris disposal locations, contact information for responsible parties, and contractor or financing details when applicable. It also includes a certification for the owner or authorized signer.

Who needs it

Property owners or their authorized applicants need this application for qualifying total demolitions or partial demolitions not covered by a building permit.

How to submit it

Submit the application to the Permit Center, 210 Lottie Street, Bellingham, WA 98225, or email [email protected].

About notarization

This application is signed and dated without a notary; the signer certifies under penalty of perjury, and no notarized attachment is identified.

How to submit this form

  1. 1

    Download The Application

    Download the Deconstruction/Demolition Permit Application PDF.

  2. 2

    Complete The Application

    Enter property, project, utility, debris-disposal, and responsible-party information, as applicable.

  3. 3

    Gather Related Information

    Provide contractor and financing details when applicable; the form identifies no required attachment.

  4. 4

    Submit To The Permit Center

    Submit the application at 210 Lottie Street or email it to [email protected].

Frequently asked questions

When is a demolition permit required?
The application says a permit is required for total demolitions of structures larger than 120 square feet and for partial demolitions when the work is not covered by a building permit.
What information does the application request?
It asks for property and project details, utilities to be removed, debris disposal locations, responsible-party contact information, and contractor or financing information when applicable.
Do I need a notary for the Deconstruction/Demolition Permit Application?
No. The signer signs and dates the application and certifies under penalty of perjury; the form does not identify a notarized attachment.
How do I submit the Deconstruction/Demolition Permit Application?
Submit it to the Permit Center at 210 Lottie Street, Bellingham, WA 98225, or email it to [email protected].

Need something notarized?

This Deconstruction/Demolition Permit Application doesn’t need a notary — but if you have another Bellingham form that does, a commissioned online notary can help.